The project comprises 5 distinct projects that were conceptualized, optimized, legalized, exploited, and operated independently. Additionally, they share common infrastructures, such as the plant electrical substation, the power evacuation, connection to the electrical substation, control system, access, fencing, CCTV, and common auxiliary services,which are typically executed by third parties.
A 138 kV power transmission line connects the plant electrical substation with the electrical substation. The power evacuation facilitates the energy transportation from the electrical substation and provides the essential communications infrastructure.
TRESCA Ingenieria was in charge of the project, which included feasibility studies and environmental processing. The basic and detailed design of the system.
- The solar plant
- Interconnection substations
- The evacuation line
WORKS: