This was the first hybrid system in Cameroon. For this hybrid solution, they have used our Fuel Save Controller equipment, which allows for the integration of inverters with a generator. The solar power system is made up of 6 Sunny Tripower 25000TL-30, a Cluster Controller S, and 6000 ATERSA 310P ultra modules.
The modules’ East and West orientation has been important for the project because the plant is in Ecuador, which makes it possible to get more performance.
TRESCA Ingenieria was in charge of defining the:
- Preliminary studies and works
- Civil works to develop wind parks
- Electrical works
- The construction of 3 substations
- The construction of 2 evacuation lines
WORKS: