GUS snack factory operated with CNG and was not connected to the Spanish grid, so it needed a 40-m3 LNG satellite plant and its regasification unit for its operation.
TRESCA Ingenieria was entrusted with the responsibility of the factory’s design, and consequently, the satellite plant’s construction management, as well as the associated purchases.
- Flexible interconnection hoses
- 2″ LNG pipes
- Cryogenic deposits
- Cryogenic pumps
- Regasification plant
- Regulation and Measurement Station
- 1 1/2″ NG piping
- Odorizer
WORKS:

Civil

Electric

Mechanical

Instrumentation and control

PROCESS

site management and supervision