![Ingeniería de detalle para la construcción del parque eólico de Cohaulia, México 199 mw Ingeniería de detalle para la construcción del parque eólico de Cohaulia, México 199 mw](https://tresca.es/wp-content/uploads/2021/10/Ingenieria-de-detalle-para-la-construccion-del-parque-eolico-de-Cohaulia-Mexico-199-mw-1200x400.jpg)
GES built the Dominica II wind farm for EGP in the State of San Luis Potosí, Mexico.
The wind farm consists of 34 wind turbines of 3 MW each, with a total installed capacity of 102 MW.
TRESCA Ingenieria was in charge of defining the:
- Basic engineering of the wind farm
- Civil and structural engineering, including the:
- Earthworks
- Design and calculation of plate foundations
- Industrial architecture and design of facilities of the control buildings and associated substations
- Buried pipelines
- Electrical and electromechanical engineering, including:
- Design and calculation of the DC Power system
- Design and calculation of the AC Power system
- Design and calculation of the Medium Voltage system
- Design and calculation of the grounding points of the Battery Cells
- Transformer centres (inverters + transformers)
- Planning of evacuation substation
- Planning of evacuation substation
- Planning of the manoeuvring substation
- Planning of the connection with existing substation
WORKS:
![Civil Civil](https://tresca.es/wp-content/uploads/2021/08/Mesa-de-trabajo-3-90x84.png)
Civil
![Mechanical Mechanical](https://tresca.es/wp-content/uploads/2021/08/Mesa-de-trabajo-5-111x90.png)
Mechanical
![Electric Electric](https://tresca.es/wp-content/uploads/2021/08/Mesa-de-trabajo-4-90x92.png)
Electric
![Instrumentation and control Instrumentation and control](https://tresca.es/wp-content/uploads/2021/08/Mesa-de-trabajo-6-80x82.png)